Moab Townhomes Entrada

Project Status

Last Updated 4/12/2018

Here’s an updated and hopefully final construction schedule! We can see light at the end of the tunnel!

Phases 4/5
405-408 Building 6 – Complete
401-404 Building 8 – Complete
501-504 Building 9 – April 19th
505-506 Building 11 – May 4th

Phases 6/7
601-604 Building 7 – Complete
701-704 Building 10 – May 4th
605-607 Building 12 – May 31st
Pavilion Pool/Pavilion – May 31st


To get current pics of the progress at the site, follow us on Facebook or Instagram (entradaatmoab).

#entradaatmoab‬ ‪#moab2016‬ ‪#moab2mountains‬ ‪#moabut‬ ‪#moabtime‬ ‪#moabadventures‬ ‪#moabcarshow‬ ‪#adventure‬ ‪#roadtrip‬ ‪#biking‬ ‪#mountainbiking‬ ‪#moabjeepsafari‬ ‪#utah‬ ‪#travel‬ ‪#hiking‬ ‪#camping‬ ‪#arches‬ ‪#archesnationalpark‬ ‪#canyonlands‬ ‪#canyonlandsnationalpark‬ ‪#4×4‬ ‪#nature‬ ‪#realesatte‬ ‪#townhome‬ ‪#condo‬ ‪#vacationrental‬ ‪#vacation‬ ‪#offroad‬ ‪#slickrock